Chris, this is what I know (not much) on how things are going-this was
as of late March:
CSX is working of Phase 4 of 5 of the New Castle Sub
resignalling plan.
Phase 1: New Castle to West End Newton Falls
Phase 2: West End Newton Falls to BD Tower (DONE)
Phase 3: BD Tower to Not
Phase 4: Not to Homerville
Phase 5: Homerville to Greenwich
As far as we're told...there will be new signals west
of Not to Homerville soon.
They skipped Phase 1 and 3 for now.
I'll try to find out more from those "in the know" maybe