I'm working on the wiring implementation plan for York, and I have a question about wire run length.
I'm thinking that, instead of tying all my feeders into a single heavier gauge bus, I'd just run them all to a centralized terminal strip (for each block).
The section of layout is only about 14' long, and any individual run would only be about half of that (7-8'), at most.
Can I get away with running the 24 AWG feeder wires for that distance? Or do I need to go up to something higher (like 16) quicker than that?